Commissioning and start-up of a 12 Mee cogeneration plant in Zalla (Vizcaya)

Service | Technical Due Diligence Técnica, Construcción project and site management.

Client | Global Efficiency Aranguren

Budget | 3,5 M€

 

Revamping of a cogeneration plant of 12 MW corresponding to the facilities of the old cellulose Plant Pastguren. The equipment consisted of a steam generator set with 18 MWt biomass boiler, a steam turbine of 12 MWe, demineralized water production facilities and electrical substation for network discharge.